'Cheesegratergate' costs construction firm millions

By Admin
Steel contractor Severfield has incurred almost £1 million of costs to date on the bolt replacement works being carried out at the Richard Rogers...

Steel contractor Severfield has incurred almost £1 million of costs to date on the bolt replacement works being carried out at the Richard Rogers-designed Leadenhall Building in the City of London, UK.

Between November 2014 and January 2015, developer British Land reported that three steel bolts had fractured and fallen from the building, which opened last July.

An investigation by contractor Laing O’Rourke and structural engineer Arup uncovered a material failure in some bolts, prompting the replacement program as a ‘precautionary measure’.

Severfield completed the original contract in 2013, but was forced to write off £10 million, admitting that it had “totally underestimated” the complexity of the job.

The steel contractor is undertaking the replacement program on the tower, commonly known as the “Cheesegrater”, in conjunction with British Land, Laing O’Rourke and Arup. It is likely to continue until the end of the calendar year.

While these works progress, all parties continue discussions to agree where the liability for the costs of the program should rest.

Severfield’s costs are being regarded as exceptional and will not impact its underlying operating profit for the current year.

In a trading update, the group added that its overall trading performance continues to be in line with management expectations. Its financial position remains “satisfactory” and net funds are expected to remain positive at the year-end, Severfield said.

The firm added that its UK order book of £194m had “strengthened further” in recent months and “provides a solid platform for a return to revenue growth in the next financial year”.

Share
Share

Featured Articles

Open ECX is transforming construction with digital solutions

Open ECX offers innovative, cloud-based e-trading solutions for the construction sector and its associated supply chain

Bechtel and CWP Global spot Africa green hydrogen potential

Partnership involving CWP Global and Bechtel to provide planning solutions for integrated configurations involving green hydrogen facilities

'Better with Bellway' sustainability strategy launched

Bellway's new sustainability strategy coincides with half-year results in which the UK homebuilder's operating profit rose 11.6% to £332.2mn

Construction of utility scale solar farms to accelerate

Construction Projects

China's longest reconstructed bridge to open early April

Construction Projects

Construction firms must focus on water neutrality

EPC