Western Construction Group Completes Historic Renovation Project in Indianapolis

By Admin
Western Waterproofing, a member company of Western Construction Group, recently completed the monumental task of restoring the deteriorated facade and e...

Western Waterproofing, a member company of Western Construction Group, recently completed the monumental task of restoring the deteriorated facade and exterior concrete of the historic Litho Press building in Indianapolis, Indiana.

A project that was originally projected to last just 3-4 months turned into a six-month project requiring 8,800 man hours, 3,500 bags of cement bag mix material and thousands of pounds of steel and lumber when demolition uncovered more severe deterioration than originally anticipated. 

The 105-year-old building, located at 800 North Capitol, had been abandoned until a redevelopment project allowed for its complete restoration to feature 111 apartment units.

The building is owned by The Whitsett Group (TWG) and Ambrose Property Group, who worked on construction for the last 15 months. The design maintained 150 industrial-designed windows to help maintain the building’s original look. The original stairwell was also retained by the developers in order to qualify for $2 million in tax credits from the National Park Service.

Western Waterproofing Project Manager Travis DeJohn said: "The engineer called out for approximately 1,500 LF of shallow depth concrete repairs not exceeding four inches in depth. Once demolition began, we discovered severed columns 20 inches in diameter and beam deterioration ranging from six to 24 inches in depth. We knew then that the number of hours and amount of materials needed to complete the job was going to escalate quickly."

Western used a combination of scissor lifts and articulating booms to complete the exterior building repairs. The entire exterior was first sounded and marked to help budget the escalating quantities. After sounding, Western removed the deteriorated concrete, replaced the steel reinforcements as needed, formed individual patches, and poured back cementitious bag mix material using five-gallon buckets.

With the scope of work drastically increasing, Western had to work overtime to try to stay within the tight timeline and budget constraints, and every detail had to be meticulously coordinated to allow several trades to complete their work simultaneously alongside one another.

Western worked closely with Indianapolis-based TWG Construction to coordinate the schedule and budget adjustments necessary to complete the project and maintain work quality.

The developers expect the finished apartments to attract a mix of students and young professionals, with forty percent of units priced at ‘affordable-housing’ level.

Share

Featured Articles

ROSHN Helping Build new Future for Saudi Arabia

Saudi community developer ROSHN on why it is is building a number of ultra-luxury housing projects along the shores of the Red Sea

Danish Hydraulics Specialist Danfoss 'Growing Sustainably'

As Danish industrial hydraulics multinational Danfoss releases its annual report for 2023, we profile the company whose technology construction relies on

Volvo CE: the Sustainable Construction Equipment Specialist

We profile Volvo Construction Equipment, which produces excavators, loaders, dump trucks & compactors to meet environmental and operational needs

Cement Industry key Target of $20bn US Decarbonisation Plan

Sustainability & Green Building

Skanska Reshapes its Sustainability Team

Sustainability & Green Building

Kingspan Group 'Cuts GHG Emissions by 65%'

Built Environment