AECOM Employs Modular Approach To Fast-Track Surgical Hubs

Share this article
Share this article
Prioritise Us on Google
A computer-generated image (CGI) of the Waterford surgical hub. Credit: O’Connell Mahon Architects
The modular approach has become a go-to method for healthcare projects such as the HSE’s surgical hubs which AECOM is delivering in the RoI

Global construction giant AECOM is using the modular approach to deliver four of six surgical hubs for the Health Service Executive (HSE) of the Republic of Ireland (ROI), which manages the country’s public health and social care services.

AECOM is employing a rapid-build construction solution, which uses a single design across three sites to help expedite the decision-making process and delivery of the projects.

“AECOM is proud to support the HSE’s efforts in this key area, building on the deep bench of expertise held by our team in Ireland as they help deliver critical infrastructure across the country, ” says Stuart Griffin, Director for Ireland at AECOM.

Stuart Griffin, Director for Ireland at AECOM

What is the modular approach?

Modular construction is a building method where structures are manufactured in repeatable sections in an off-site factory and then assembled on a building site.

While the modular approach has existed in construction for at least 200 years, the industry is now using the method to address current pressing challenges.

These include global labour shortages due to an ageing workforce and the reduction of new talent entering the industry, slow construction-productivity growth, housing shortages and CO2 emissions.

Modular construction is helping enhance the industry’s productivity, reducing the need for manpower by up to 40%, and accelerating timelines by up to 50%, says management consulting firm, McKinsey & Company.

It can also help save costs when executed properly and at scale, while also potentially reducing CO2 emissions.

As McKinsey highlights, developments in technology, data and automation are helping construction companies optimise the approach. 

For example, new digital platforms can connect customers across the ecosystem with suppliers, while also allowing companies to more easily customise and enhance their designs for specific sites.

McKinsey has identified more than 700 companies currently operating in modular construction. More than 100 have existed for 50 years or more. However, more than 200 companies were founded in the past 20 years.

A fragmented modular construction sector

According to McKinsey’s analysis the modular construction sector consists of a few large players and a long tail of more than 500 smaller ones with less than €50m (around US$57m) in revenue. 

Overall, it reveals that most companies in the sector are successful, showing robust profitability or strong growth, with those using the modular construction method on permanent buildings weighted an average EBITDA of approximately 7%.

However, it should be noted that while some companies have scaled in size in recent years, and even grown to international level, there have been a few bankruptcies. Profitability varies significantly for companies in the sector.

Vertically integrated companies tend to fare better than others. For example, firms operating in modular manufacturing and assembly tend to have higher earnings before interest, taxes, depreciation and amortisation margins (EBITDA), averaging around 15 to 20% EBITDA compared to companies that only offer modular manufacturing, which average 5% EBITDA.

The success of these vertically integrated firms can be specifically attributed to their broader scope, their ability to organise more efficiently as their teams are specifically trained to cover a broader modular system, and their minimal pass-through of costs to subcontractors. 

While around 60% of players serve the single-family homes segment, profitability appears to be higher for firms which deliver more specialised assets, such as hotels and healthcare facilities.

AECOM’s ROI surgical hub projects

Youtube Placeholder

Demand for healthcare in Ireand is at an unprecedented high. The HSE’s surgical hubs are meant to reduce waiting times ahead of the rollout of its Elective Hospital programme, a major healthcare reform initiative which is designed to separate scheduled (routine) procedures from unscheduled emergency care to reduce patient waiting lists.

Elective hospitals will eventually serve Dublin, Cork and Galway.

The surgical hubs will operate from:

Cork University Hospital (complete and operating from 28 September)

University Hospital Waterford 

University Hospital Limerick’s O’Connell Avenue 

Merlin Park University Hospital Galway 

Located in key locations in Ireland’s regional cities, the hubs range in size from 5,000 square metres to 6,000 square metres, with each including operating theatres and associated theatre department support and storage areas.

They also include consultant exam rooms, procedure rooms, post-operative recovery, staff facilities and public and patient changing facilities.

“These new hubs will improve our healthcare system’s capacity to deliver high-volume, low-complexity procedures – reducing waiting times for patients and ensuring they have direct access to key health services at a regional level,” says Stuart.

At the centre of AECOM’s strategy is the delivery of the Cork, Waterford and Limerick sites as quickly as possible and in parallel.

To achieve this, the company has adopted a single standardised design solution that it is applying to each site location. It is based on the design used for the Reeves Day Surgery Centre at Tallaght University Hospital, another one of its projects.   

“Implementing a standard design approach has been pivotal in accelerating the delivery of this critical programme. By using standardised designs and aligning teams across multiple sites, we’ve been able to accelerate delivery while maintaining the highest standards – ensuring patients will be able to benefit from these facilities as quickly as possible,” explains Brian O’Connell, National Director, Head of Strategic Infrastructure and Capital Delivery, Health Service Executive.

Brian O’Connell, National Director, Head of Strategic Infrastructure and Capital Delivery, Health Service Executive

The standard design approach required simultaneously maintaining consistency, control and coordination of the projects , which AECOM says facilitated a cohesive delivery across the three sites.

All stakeholders had to make decisions based on programme-level considerations and requirements rather than focusing on a single location.

AECOM therefore took a holistic approach for each stage of the projects with the three sites being procured under a single tender process. 

It also applied the same approach to cost management, allowing consistent planning and budget targets, cost forecasting and performance data to maintain alignment across the three sites. 

The collaborative, standard design approach has proven successful, says AECOM, with planning applications lodged within four months and approvals secured within ten months of the appointment of the teams by HSE. 

Overall, using standardised designs, helped it deliver multiple projects efficiently – despite constrained industry resources. 


AECOM’s key partners:

HSE (Health Service Executive)

The government agency that manages all public health and social care services in the Republic of Ireland and the client on the surgical hubs programme.

JJ Rhatigan

The design-and-build contractor for the Limerick, Waterford and Cork hubs, on a €162m (US$184m) project with construction having started in September 2024.

O'Connell Mahon Architects (OCMA)

O'Connell Mahon Architects (OCMA) led the integrated design team, working with the HSE and JJ Rhatigan as D&B partners, and was novated to the contractor.

Executives

  • Brian O'Connell

    National Director Head of Strategic Health Infrastructure and Capital Delivery

  • Stuart Griffin

    Director, Infrastructure Project & Cost Management Lead, Ireland