China's longest reconstructed bridge to open early April

Reconstruction involves the simultaneous lifting of two 15m-wide bridges on north and south sides of 1,792m Yihe Bridge says Tianyuan Construction Group

China's largest and longest bridge jacking reconstruction project by area and length will complete early April, according to Tianyuan Construction Group.

Located on Beijing Road in the south of Linyi city in Shandong province, Yihe Bridge was 1,210.72m-by-23m with a jacking height of 1,050m. After renovation, it will be 1,792m-by-52m.

"The successful completion of the Beijing Road Yihe Bridge jacking project will greatly ease the traffic situation between Beicheng New District and Hedong District," said Li Baoqiang, who is in charge of the reconstruction project.

Reconstruction involves the simultaneous lifting of two new 15m-wide bridges on the north and south sides of Yihe Bridge. The entire upper structure of the old bridge will be lifted by 2.57m. The lifting of the northern and southern sections was completed in November 2021 and February 2022 respectively.

Currently, the cover beam of the southern section is being heightened and is on track for completion in early April. The entire project is planned to complete before October 1, which will ensure that traffic on both sides of the Yi River is smooth, spurring the regional economy.

Main construction challenges faced with China's longest reconstructed bridge

In order to ensure safety during the bridge jacking process and ensure that equipment is stable, 19 sets of limiters were installed on the bridge deck, preventing vertical and horizontal displacement of the beam body during the jacking process.

Beijing Road Yihe Bridge was lifted via an alternate lifting process. This process involves two sets of jacks being lifted synchronously underpinned by support. This method allows for continuous lifting of the entire jacking process, ensuring efficiency and control. Furthermore, a PLC hydraulic synchronous control system was incorporated to ensure synchronization and structural safety.

Reasons for bridge jacking during construction process

As Beijing Road Yihe Bridge is a transportation hub connecting New Beicheng and Hedong districts, it is important that it functions well and safely. Bridge jacking is essential for the repair and maintenance of bridges.

In November 2019, dynamic and static load tests were carried out on Beijing Road Yihe Bridge. The tests showed that the bridge met bearing capacity requirements and had sufficient safety reserves. Therefore, there was no need to demolish the old bridge.

To meet flood control requirements, in which the minimum elevation of the bottom beam has to be 0.8m higher than the 100-year flood level of 72.36m, the superstructure of the old bridge also had to be raised by 2.57m.

Furthermore, the current bridge is supported by a 30m-wide simple support box girder. However, as there are many piers and columns under the bridge, a 60m-wide girder was recommended instead for a better bridge view.

Share

Featured Articles

Arcadis signs collaboration with Canadian start-up Niricson

Agreement will combine Arcadis’ expertise with Niricson’s predictive analytics platform to develop a non-invasive way to safely inspect and monitor concret

Italy’s Cannon Artes wins $31m Egyptian desalination project

Turnkey contract win from SOPC will see Italian firm deliver an integrated desalination & demineralisation plant as part of modernisation of Suez refinery

Saudi Arabia to build three new stadiums for Asian Cup 2027

Tournament will be hosted across three cities and 10 stadiums, SAFF says

Neoen’s Storen Power Reserve begins construction in Sweden

Construction Projects

Masdar works with African countries on renewable projects

Construction Projects

Select Group awards US$816.7m in construction contracts

Construction Projects