Contractor issues head disputes list in 2020: Arcadis report

By Dominic Ellis
The average value of disputes globally rose to $54.26 million in 2020 - but the numbers were much the same as 2019, according to an Arcadis report

The average value of disputes globally rose from $30.7 million in 2019 to $54.26 million in 2020, while the length of disputes fell from 15 months in 2019 to 13.4 months, according to an Arcadis report.

The data, featured in Arcadis' 11th annual report, illustrates industry-wide ripple effects of the COVID-19 pandemic although interestingly the overall volume of disputes stayed relatively the same in 2020 as in 2019.

While trends in the value and length of disputes varied from region to region, all regions surveyed saw an increase in "mega disputes" related to bigger capital programs and private projects. Notably, more than 60% of survey respondents encountered project impacts due to COVID-19.

Owners, contractors, or subcontractors failing to understand and/or comply with their contractual obligations became the leading cause of construction disputes in 2020 (jumping from 3rd place in 2019), followed by owner-directed changes and third-party or force-majeure changes as the second and third-leading causes, respectively.

Highlights from the report include:

  • Proper contract administration was a theme across the globe for the successful and early resolution of disputes
  • Most disputes were settled through party-to-party negotiation, and a willingness to compromise played a key role in early resolution
  • Among regions surveyed, the buildings (education, healthcare, retail/commercial, government) sector saw the most disputes
  • In North America, construction dispute value rose from $18.8 million in 2019 to $37.9 million in 2020, while the length of disputes shortened from 17.6 to 14.2 months.

While cost and length have changed since 2019, risk management was still seen as the most effective claims avoidance tactic, while owner/contractor willingness to compromise was once again the top-ranked factor for the mitigation/early resolution of disputes.

"COVID-19 irrevocably changed every industry," said Roy Cooper, head of contract solutions for Arcadis North America. "Construction disputes experts will have to continue to adapt, even post-pandemic, as workforce expectations, climate events and government infrastructure funding change how projects are designed and contracted in the future."

The research presented in the report was compiled by Arcadis based on survey responses, global construction disputes the team handled in 2020 and contributions from industry experts.

Share

Featured Articles

Neoen’s Storen Power Reserve begins construction in Sweden

Notice to Proceed given to Nidec at the end of December 2022, French renewable energy producer says

Masdar works with African countries on renewable projects

Agreements with Angola, Uganda and Zambia will see development of renewable energy projects with a combined capacity of up to 5GW

Select Group awards US$816.7m in construction contracts

Contracts awarded cover more than 10 million square feet of development and are for development projects launched over the last year

Saipem awarded $1.2bn contracts for Guyana and Egypt project

Construction Projects

Saudi Arabia dominates MENA construction sector in 2022

Facilities Management

WeBuild-led consortium signs €1.26bn Italian highway contrac

Construction Projects